Ongoing Projects

Home Ongoing Projects
NAME OF PROJECT / KIND OF WORKS VALUE OF WORKS (ETB) PERIOD OF CONTRACT PERCENTAGE OF WORK COMPLETED CLIENT & PLACE
Dire Dawa Old Stadium Expansion Project 212,336,851.48 Dec 2015 to Dec 2017 70% Dire Dawa Administration Youth & Sport Commision
Construction of G+4 commercial Building 33,591,784.07 May 2015 To May 2017 95% Lucy Engineering PLC
Dire Dawa Hospital Referal Hospital Site Work 67,859,416.20 July 2016- Oct 2017 60% Dire Dawa Administration Health Office
Construction of G+1 Resource Center 32,575,289.16 June 2016 to Dec 2017 60% Dire Dawa Administration Education Bureau
Construction of G+5 office Building project 206,556,488.53 June 2017 - June 2019 - Dire Dawa Administration construction and housing Bureau
Construction of G+2 Management Training Center 170,310,279.35 June 2017 - June 2020 - Dire Dawa Administration Civil Service Bureau
Assela Zonal Post Office Building 30,081,878.08 June 2017 - June 2018 - Dire Dawa Administration Civil Service Bureau